Sewage plant As Samra, Jordan - With the selected PERI formwork and scaffolding systems, the construction team was able to cost-effectively fulfil all requirements in spite of the tight construction schedule. The solutions developed by PERI engineers and the local site management, along with support provided by PERI specialists, contributed to efficient and problem-free construction.

Sewage plant As Samra
Samra, Jordan

Large-size sewage plant with about 60 individual buildings

Construction period: 2004 - 2006

 

 

Location
Main Application
Infrastructure
Project participants
Customer: Morganti Group, Inc., USA

The Project

Impressions from the project process

Project Information

Ghassan A. Kawash, Project manager, Statement Samra
Ghassan A. Kawash, Project manager, Statement Samra
Ghassan A. Kawash
Project manager
PERI was able to offer us comprehensive and workable solutions. The applied formwork and scaffolding systems were very versatile and easy to install. Also the cooperative collaboration with PERI was consistently positive.
Interested in learning how PERI can support your next project?

Call us on +971 (0) 4 326 2992 to discuss your requirements further.

Location

Sewage plant As Samra, Jordan

Sewage plant As Samra, Jordan - With the selected PERI formwork and scaffolding systems, the construction team was able to cost-effectively fulfil all requirements in spite of the tight construction schedule. The solutions developed by PERI engineers and the local site management, along with support provided by PERI specialists, contributed to efficient and problem-free construction.
Sewage plant As Samra, Jordan - With the selected PERI formwork and scaffolding systems, the construction team was able to cost-effectively fulfil all requirements in spite of the tight construction schedule. The solutions developed by PERI engineers and the local site management, along with support provided by PERI specialists, contributed to efficient and problem-free construction.