![beeah-hq-main The main Dome being built with PERI UP scaffolding and working platforms](https://cdn.peri.cloud/.imaging/mWide/dam/a683dc72-fde2-4724-939c-c90e4adff83c/61456/beeah-hq-main.jpg)
The Project
Impressions from the project process
The basic panels complete assembly with PERI UP shoring system and GT24 in a special solution
PERI UP shoring supporting the basic panels at the last pouring stage
Basic panels being assembled simultaneously from both sides
Curved walls casted with VARIO GT24 wall system
First shells being installed on one side of the dome at stage 1
Shells being prepared for installation on right side of the dome
Special PERI solution with basic panels at stage one
Circular basic panels assembled on all stages
The main Dome being built with PERI UP scaffolding and working platforms
PERI UP is used to reach the top of the Dome at 15.3m high
Finalizing the top of the Dome with PERI special and customized panels
Customized box-outs offered for this special structure of the main Dome
![Basic panels complete assembly with PERI UP shoring system and special solution](https://cdn.peri.cloud/.imaging/mWide/dam/ae127422-fd12-4df0-8583-a270a89cb951/61375/peri-up-with-basic-panels-and-gt24.jpg)
![PERI UP with basic panels and GT24 Basic panels complete assembly with PERI UP shoring system and special solution](https://cdn.peri.cloud/.imaging/mWide/dam/ae127422-fd12-4df0-8583-a270a89cb951/61375/peri-up-with-basic-panels-and-gt24.jpg)
![PERI UP shoring supporting the basic panels at the last pouring stage](https://cdn.peri.cloud/.imaging/mWide/dam/5394a8d5-e4bb-4231-851c-9a3922c65a6e/61361/last-stage-basic-panels.jpg)
![Last stage basic panels PERI UP shoring supporting the basic panels at the last pouring stage](https://cdn.peri.cloud/.imaging/mWide/dam/5394a8d5-e4bb-4231-851c-9a3922c65a6e/61361/last-stage-basic-panels.jpg)
![Basic panels being assembled simultaneously from both sides](https://cdn.peri.cloud/.imaging/mWide/dam/99ec17a1-78d6-4122-85fe-23ea4dad0d09/61362/first-stage-basic-panels-assmbly.jpg)
![First stage basic panels assmbly Basic panels being assembled simultaneously from both sides](https://cdn.peri.cloud/.imaging/mWide/dam/99ec17a1-78d6-4122-85fe-23ea4dad0d09/61362/first-stage-basic-panels-assmbly.jpg)
![Curved walls casted with VARIO GT24 wall system](https://cdn.peri.cloud/.imaging/mWide/dam/02fe9d03-b427-49a4-bece-255147ed1701/61364/vario-gt24-wall.jpg)
![VARIO GT24 wall Curved walls casted with VARIO GT24 wall system](https://cdn.peri.cloud/.imaging/mWide/dam/02fe9d03-b427-49a4-bece-255147ed1701/61364/vario-gt24-wall.jpg)
![First shells being installed on one side of the dome](https://cdn.peri.cloud/.imaging/mWide/dam/1f049d2d-0fd6-44d8-9da4-3f27804be638/61367/left-side-first-shells-installed.jpg)
![Left side first shells installed First shells being installed on one side of the dome](https://cdn.peri.cloud/.imaging/mWide/dam/1f049d2d-0fd6-44d8-9da4-3f27804be638/61367/left-side-first-shells-installed.jpg)
![Shells being prepared for installation on right side of the dome](https://cdn.peri.cloud/.imaging/mWide/dam/ee165bb9-be59-4a54-8f56-25b11312b7e7/61449/right-side-of-the-dome-without-shells.jpg)
![Right side of the dome without shells Shells being prepared for installation on right side of the dome](https://cdn.peri.cloud/.imaging/mWide/dam/ee165bb9-be59-4a54-8f56-25b11312b7e7/61449/right-side-of-the-dome-without-shells.jpg)
![Special PERI solution with basic panels at stage one](https://cdn.peri.cloud/.imaging/lPortrait/dam/a64491fd-4880-4b21-8c2a-3fd38745cd4a/61451/basic-panels-at-stage-1-and-2.jpg)
![Basic panels at stage 1 and 2 Special PERI solution with basic panels at stage one](https://cdn.peri.cloud/.imaging/lPortrait/dam/a64491fd-4880-4b21-8c2a-3fd38745cd4a/61451/basic-panels-at-stage-1-and-2.jpg)
![Circular basic panels assembled on all stages](https://cdn.peri.cloud/.imaging/mWide/dam/dd235d8d-0329-484b-932a-0918ebe234fd/61453/complete-basic-panels.jpg)
![Complete basic panels Circular basic panels assembled on all stages](https://cdn.peri.cloud/.imaging/mWide/dam/dd235d8d-0329-484b-932a-0918ebe234fd/61453/complete-basic-panels.jpg)
![The main Dome being built with PERI UP scaffolding and working platforms](https://cdn.peri.cloud/.imaging/mWide/dam/a683dc72-fde2-4724-939c-c90e4adff83c/61456/beeah-hq-main.jpg)
![beeah-hq-main The main Dome being built with PERI UP scaffolding and working platforms](https://cdn.peri.cloud/.imaging/mWide/dam/a683dc72-fde2-4724-939c-c90e4adff83c/61456/beeah-hq-main.jpg)
![PERI UP is used to reach the top of the Dome at 15.3m high](https://cdn.peri.cloud/.imaging/mWide/dam/a915bc87-3eca-467e-a7ab-3c6c9e8dbc16/61442/peri-up-scaffolding-system-offering-safe-access-to-the-top.jpg)
![PERI UP Scaffolding system offering safe access to the top PERI UP is used to reach the top of the Dome at 15.3m high](https://cdn.peri.cloud/.imaging/mWide/dam/a915bc87-3eca-467e-a7ab-3c6c9e8dbc16/61442/peri-up-scaffolding-system-offering-safe-access-to-the-top.jpg)
![Finalizing the top of the Dome with PERI special and customized panels](https://cdn.peri.cloud/.imaging/mWide/dam/f69d0fc9-1017-40c7-af6f-7c22a6638366/61444/bee-ah-hq-closing-the-dome.jpg)
![Bee'ah HQ closing the Dome Finalizing the top of the Dome with PERI special and customized panels](https://cdn.peri.cloud/.imaging/mWide/dam/f69d0fc9-1017-40c7-af6f-7c22a6638366/61444/bee-ah-hq-closing-the-dome.jpg)
![Customized box-outs offered for this special structure of the main Dome](https://cdn.peri.cloud/.imaging/mWide/dam/bac9fd6b-0a15-4b6c-9905-7b5c92538eec/61446/main-dome-being-built-with-peri-box-outs.jpg)
![Main Dome being built with PERI box-outs Customized box-outs offered for this special structure of the main Dome](https://cdn.peri.cloud/.imaging/mWide/dam/bac9fd6b-0a15-4b6c-9905-7b5c92538eec/61446/main-dome-being-built-with-peri-box-outs.jpg)
![PERI UP with basic panels and GT24 Basic panels complete assembly with PERI UP shoring system and special solution](https://cdn.peri.cloud/.imaging/mWide/dam/ae127422-fd12-4df0-8583-a270a89cb951/61375/peri-up-with-basic-panels-and-gt24.jpg)
The basic panels complete assembly with PERI UP shoring system and GT24 in a special solution
![Last stage basic panels PERI UP shoring supporting the basic panels at the last pouring stage](https://cdn.peri.cloud/.imaging/mWide/dam/5394a8d5-e4bb-4231-851c-9a3922c65a6e/61361/last-stage-basic-panels.jpg)
PERI UP shoring supporting the basic panels at the last pouring stage
![First stage basic panels assmbly Basic panels being assembled simultaneously from both sides](https://cdn.peri.cloud/.imaging/mWide/dam/99ec17a1-78d6-4122-85fe-23ea4dad0d09/61362/first-stage-basic-panels-assmbly.jpg)
Basic panels being assembled simultaneously from both sides
![VARIO GT24 wall Curved walls casted with VARIO GT24 wall system](https://cdn.peri.cloud/.imaging/mWide/dam/02fe9d03-b427-49a4-bece-255147ed1701/61364/vario-gt24-wall.jpg)
Curved walls casted with VARIO GT24 wall system
![Left side first shells installed First shells being installed on one side of the dome](https://cdn.peri.cloud/.imaging/mWide/dam/1f049d2d-0fd6-44d8-9da4-3f27804be638/61367/left-side-first-shells-installed.jpg)
First shells being installed on one side of the dome at stage 1
![Right side of the dome without shells Shells being prepared for installation on right side of the dome](https://cdn.peri.cloud/.imaging/mWide/dam/ee165bb9-be59-4a54-8f56-25b11312b7e7/61449/right-side-of-the-dome-without-shells.jpg)
Shells being prepared for installation on right side of the dome
![Basic panels at stage 1 and 2 Special PERI solution with basic panels at stage one](https://cdn.peri.cloud/.imaging/lPortrait/dam/a64491fd-4880-4b21-8c2a-3fd38745cd4a/61451/basic-panels-at-stage-1-and-2.jpg)
Special PERI solution with basic panels at stage one
![Complete basic panels Circular basic panels assembled on all stages](https://cdn.peri.cloud/.imaging/mWide/dam/dd235d8d-0329-484b-932a-0918ebe234fd/61453/complete-basic-panels.jpg)
Circular basic panels assembled on all stages
![beeah-hq-main The main Dome being built with PERI UP scaffolding and working platforms](https://cdn.peri.cloud/.imaging/mWide/dam/a683dc72-fde2-4724-939c-c90e4adff83c/61456/beeah-hq-main.jpg)
The main Dome being built with PERI UP scaffolding and working platforms
![PERI UP Scaffolding system offering safe access to the top PERI UP is used to reach the top of the Dome at 15.3m high](https://cdn.peri.cloud/.imaging/mWide/dam/a915bc87-3eca-467e-a7ab-3c6c9e8dbc16/61442/peri-up-scaffolding-system-offering-safe-access-to-the-top.jpg)
PERI UP is used to reach the top of the Dome at 15.3m high
![Bee'ah HQ closing the Dome Finalizing the top of the Dome with PERI special and customized panels](https://cdn.peri.cloud/.imaging/mWide/dam/f69d0fc9-1017-40c7-af6f-7c22a6638366/61444/bee-ah-hq-closing-the-dome.jpg)
Finalizing the top of the Dome with PERI special and customized panels
![Main Dome being built with PERI box-outs Customized box-outs offered for this special structure of the main Dome](https://cdn.peri.cloud/.imaging/mWide/dam/bac9fd6b-0a15-4b6c-9905-7b5c92538eec/61446/main-dome-being-built-with-peri-box-outs.jpg)
Customized box-outs offered for this special structure of the main Dome
![Hamish James, Project Director - Al Futtaim Carillion](https://cdn.peri.cloud/.imaging/xlWide/dam/b88c9300-c3d7-439e-896c-56c245041bcc/61466/project-director.jpg)
![Project Director Hamish James, Project Director - Al Futtaim Carillion](https://cdn.peri.cloud/.imaging/xlWide/dam/b88c9300-c3d7-439e-896c-56c245041bcc/61466/project-director.jpg)
Hamish James
![The main Dome being built with PERI UP scaffolding and working platforms](https://cdn.peri.cloud/.imaging/mWide/dam/a683dc72-fde2-4724-939c-c90e4adff83c/61456/beeah-hq-main.jpg)
![beeah-hq-main The main Dome being built with PERI UP scaffolding and working platforms](https://cdn.peri.cloud/.imaging/mWide/dam/a683dc72-fde2-4724-939c-c90e4adff83c/61456/beeah-hq-main.jpg)