Al Falah Villas - Abu Dhabi, UAE

Project data

Location: Abu Dhabi, United Arab Emirates

  • Residential villa complex
  • Total of 899 villas
  • Project start date: July 2019
  • Completion date: November 2021

Requirements

  • Flexible scaffolding system for finishing works
  • System that would be easy to use on site
  • Quick erection and dismantling required for fast progress
  • Minimum use of tubes and couplers
  • Safe system for team on site

Customer

Trojan General Contracting

Customer's benefit

  • Quick and efficient progress
  • High productivity: 1 villa/day
  • Increased safety for site team
Project Manager - Al Falah Villas, Abu Dhabi
Eng. Mohamed Adnan Yassine
Project Manager

We were immediately impressed by PERI UP's multifunctional aspect. It can be used as external scaffolding as well as heavy duty shoring. Our team quickly adapted to the system which made operations on site go smoothly and more importantly, without any delays.

PERI solution

  • 55 sets of PERI UP Façade Scaffolding system used for a total of 450 villas
  • UDG Decks
  • Hatch and ladder
  • Toe boards for additional safety