Badr project - Dubai, UAE

Project data

Location: Dubai, United Arab Emirates

  • 11 commercial / residential low-rise buildings
  • Floors: ranging from 3 to 7
  • GF: 80,000 m/ Typical floor: 3,000 - 5,000 m2
  • Construction period: 2016 - 2018 | 24 months

Requirements

  • Project demanding high quality finishing
  • Quick and practical system due to tight construction schedule
  • Familiar system that is easy to use and popular among site personnel

Customer

Engineering Contracting Co.

Customer's benefit

  • Flexible combination of SKYDECK with props and PERI UP shoring system to adapt according to the site requirements
  • Economical LICO system with fast assembly time and flexible panel sizes which allowed the site to be ahead of schedule with the columns
Nasser Nasser - Construction Manager at ECC for Al Badr project with PERI
Nasser Nasser
Construction Manager

The reason we chose to work with PERI on this project is the practical and high quality aspect of the products. SKYDECK is ideal for slabs as it is independent of a crane, especially for big areas like this one. LICO is the best choice for columns as it is highly economical and we were able to save on plywood costs. Also the cooperation with the sales and supervision team on site was excellent.

PERI solution

  • 30,000 mof SKYDECK slab formwork system, with a pouring cycle of 7 days for each floor, allowing to maintain the schedule as planned
  • 15,000 m2 of PERI UP shoring system used on the GF and 1st floor, for slab support at heights of 6m
  • 114 set of LICO column formwork, that allowed for a very fast and economical process, and a high flexibility in terms of panel sizes and adjustments.